With the exception of paving, the 4th Street Water Main Replacement project is complete. We are waiting for confirmation from our contractor on an exact start date for the mill and overlay of this area. Mill and overlay will take place on Davis Street and 4th Street south of Maag Street. We expect this work to commence the week of November 7th.
The 2016 Sidewalk Project includes replacement of the sidewalk in Legion Park, behind the Community Center and removal of the sidewalk on North 3rd Street. This project is under contract and has a required completion date of November 11th.
We continue to move forward with planning the reconstruct of North 2nd Street from Ferry to Grove for 2017.
We will continue to provide updates as these projects progress. Again, thank you for your continued patience.
CenterPoint Energy has been in the process of restoring gas main project areas for the last several months. This includes street patching on Ferry Street and 4th Street (North of Ferry St.) along with other areas throughout town. If you have concerns about project restorations, we encourage you call CenterPoint Energy at (612) 321-5042 (Project ID # 73083899). If you have project questions, please call (612) 321-5369.
City staff contacted CenterPoint Energy on November 2nd in regard to our concern with the restoration of this project. They will be sending out a representative today to look into the restoration work.